BACKGROUND

Why these standards now

On 10 July 2024, a lightning arrester failed on a 230 kV transmission line in Northern Virginia. Automatic reclosing turned one fault into six within 82 seconds. Each fault was cleared normally, but each pulled local voltage down to 0.25–0.40 p.u. — and nearby data centers moved about 1,500 MW of load to backup power on their own. No utility equipment disconnected them. Around 1,260 MW, which left at the third dip, stayed off for hours: a common protection scheme moves a facility to backup after three disturbances within a minute and keeps it there until it is reconnected by hand.1,2

Faulted-phase voltage at a nearby station on 10 July 2024: six sharp dips between 7:00:23 and 7:01:45 p.m.
Six voltage dips in 82 seconds as the line reclosed onto the fault. Source: NERC Incident Review, January 2025, Figure 1 ↗
Area load on 10 July 2024: a step drop of about 1,500 MW near 7 p.m. that did not recover for hours.
About 1,500 MW of data-center load lost; most did not return for hours. Source: NERC Incident Review, January 2025, Figure 2 ↗

The pattern since

WhenWhat happenedLoad
10 Jul 2024 · Northern Virginia (PJM)Six faults in 82 seconds on one 230 kV line; nearby data centers transfer to backup power.1,2≈1,500 MW; most off for hours
21 May 2026 · ERCOT (planning study)ERCOT screens about 20 GW of large loads: four groups would not ride through a single three-phase fault on the 345 kV system in its 2028 planning case.45.4–6.0 GW per group could trip
22 Jul 2026 · Northern Virginia (PJM)A mechanical failure takes out one 230 kV line; data-center load transfers to backup in two steps, 67 seconds apart.3≈3,800 MW — the largest load transfer PJM has recorded; back within about 30 minutes

Regulators responded. ERCOT NOGRR 282, in force since 1 August 2026, makes voltage ride-through and post-fault active power recovery mandatory for large computational loads.6 NERC issued a Level 3 alert on computational loads in May 2026 and is developing continent-wide standards.5 Inside OCP, the Data Center Facility project published an Interface Specification Between Hyperscalers and Utility Grid for Disturbance Performance (V1.0.0, September 2026) that states the same commitment at the point of interconnection.7 The events exposed a gap between today's rack power design and grid interconnection requirements.8,9

REGULATORY REQUIREMENTS

Standards XMight's POM implementation is designed against

ERCOT · NOGRR 282

Post-Fault Active Power Recovery

Return to at least 90% of pre-disturbance load within 2 seconds of voltage recovery.6

ERCOT Nodal Operating Guide · NOGRR 282

In force since 1 August 2026

XMight's POM implementation is designed to support site-level compliance with this requirement.

WHERE THIS IS HAPPENING

Selected large-load ride-through initiatives.

ERCOT NOGRR 282 is in force. The others are at different stages, from draft to adopted.10

Region Authority / TSO Regulation Timeline
US / Canada — continent-wide NERC Reliability Guideline (May 2026, voluntary) + Project 2026-02 standards Guideline May 2026 · mandatory standards due to FERC by 31 Dec 2026 (RD26-7-000)
US — Texas ERCOT NOGRR 282 + NPRR 1308 In force since 2026/08 · 0.50–0.80 p.u. continued-consumption step-up 2028/01
US — California CAISO Large Loads Technical Requirements (Stakeholder WG) Issue Paper 2026-01 · Straw Proposal April 2026
US — Virginia Dominion Energy Facility Interconnection Reqs. In effect (case-by-case)
US — Central SPP RR 696 (HILL) + HILL FRT v1.0 RR 696 approved 2025/9 · FRT v1.0 2025/8
Canada — Ontario IESO TR for Large Computational Loads v1.0 Published 2026-05-01 · stakeholder feedback to 2026-05-28
Ireland EirGrid + SONI MPID345 Grid Code Mod. (draft) Draft 2025/11 · Rollout 2026 – 2028
Germany VDE FNN VDE-AR-N 4130 + A1 amendment A1 draft 2025/10–11 (revising)
Australia AEMC + AEMO Draft Rule (Large IBL ≥ 30 MW) Final rule mid-2026